PERT = (O+4M+P) / 6 ; PERT Project duration = Sum of PERTS
STD of activity (STD) = (P-O)/6
Variance of activity = [STD]2 = [(P-O)/6] 2
STD of project = +var1 + var2 +...
Project Duration = Sum of PERTs ± (# of sigma’s * STD of project)

Present Value : FV/(1+r ) n (Please read as FV devide by (1+r) power n)



FV=Future value; r=Rate of interest
n = number of time periods

Communication Channels = N (N-1)/2
Where N is the number of stackholders

Communication channel question can be very tricky.. so please use it very carefully